РефератыИностранный языкBuBusiness NPV Essay Research Paper The NPV

Business NPV Essay Research Paper The NPV

Business NPV Essay, Research Paper


The NPV is £56700 for the


project given the best estimate cash flows. Therefore under the assumption that


the firm is operating to maximise the market value of their common stock, and


under the assumed conditions of certainty of prices of all assets, the firm


should accept the project, as the NPV is positive. This will increase the value


of the firm as long as no other groups of projects can be found which will


increase the value of the firm.B)The project has 2 internal


rates of return (multiple IRR?s) that are 4.8% and 13.45%.? Affects of multiple IRR?s are shown in graph


1.? The discount rate exceeds 4.8%


the proposal becomes positive and at 13.45% the present value of all the cash


flows is 0.? Therefore when the cost of


capital is between 4.8% and 13.45% the NPV is positive, and following the NPV


rule the project should be accepted.?


However if the IRR calculation of 4.8% is used the project maybe


incorrectly rejected as the cost of capital is in excess of 4.8%. Graph 1


however indicates this is an incorrect decision when the cost of capital is


between 4.8% and 13.45%.C)Both the IRR and the NPV


take account of time value of money, but situations arise where the IRR method


leads to different decisions being made from those that would implement the NPV


method.Mutually exclusive


projects exist when there is


acceptance of one project excludes the acceptance of another. The following


example will illustrate how the NPV and the IRR lead to different decisions. ??????????????????????????????????? Initial


Investment Outlay?? Net Inflow End Of Year


(£)??????????????????????????????????????????????? ??????????????????????????????????????????????? ??????????????????????????????????????????????????????????????????????????????????????????????? 1????????? 2????????? 3????????? Project A?????????????????????????????? £7000???????????????????????????????????? 3430?? 3430?? 3430 Project B?????????????????????????????? £12000?????????????????????????????????? 5520?? 5520?? 5520 Cost of Capital = 10% The NPV and IRR calculations


are as follows: ??????????????????????????????????????????????? ??????????????????????????????????????????????? IRR (%)????????? NPV (£) Project A?????????????????????????????? 22??????????????????? 1530 Project B?????????????????????????????? 18??????????????????? 1728 ??????????????????????????????????????????????????????????????????????????????????? Source:


Principles of Corporate ??????????????????????????????????????????????????????????????????????????????????? ? ????????? ?Finance, 6th edition ??????????????????????????????????????????????????????????????????????????????????? ? ????????? ?Brealy and Myers The IRR ranks A first


and NPV ranks B first.? If


the projects were independent this would be irrelevant, since both would be


accepted.? However the case is mutually


exclusive, therefore raking is crucial.?


Graph 2 illustrates this. A discount rate greater than


12% no contradictions arise, below 12% project B has higher NPV and


project A has a higher IRR.? The


IRR gives incorrect ranking proved by considering the increments of cash flows


of project B over A. Years ??????????????????????????????????????????????? 0????????? 1????????? 2????????? 3 ??????????????????????????????????????????????? (£)?????? (£)?????? (£)?????? (£) Project A?????????????????????????????? 120005520?? 5520?? 5520 Project B?????????????????????????????? 7000?? 3430?? 3430?? 3430 Incremental Cash Flow???? 5000?? 2090?? 2090?? 2090 If the firm did use the IRR


method and chose product A, we can establish if it is worthwhile to the


incremental investment (B-A). The acceptance of this investment + incremental


investment = A + (B-A), this is = to accepting project B.? Firm therefore accepts the incremental


investment.? Using the IRR rule is the


same as moving from A to B.? The IRR of


the incremental investment is (B-A) 12%.?


The cost of capital is 10%, the incremental project should be accepted,


as the IRR rule indicated a move from A to B.?


The superiority of the NPV method has been established, using the IRR


analysis to contradict the IRR rule.The IRR expresses results


as a percentage.? This is misleading; for example, compare an


investment of £100 that yields 50% return, with an investment of £1000 that


yields 25%.? If one project can be


accepted, the first will yield £50 and the second £250.? If the cost of capital is 10%, surplus fund


will be invested at the cost of capital.?


The first investment will be £90 + the £50 return from the £100 =


£140. Clearly the second investment, which yields a return of £250, is


preferred, as the objective of the firm is to maximise the firm?s wealth, so


the NPV provides the correct measure.Where there are unconventional


cashflows the IRR has a shortcoming.?


If the signs of net cash flows changes over successive periods,


calculations could produce as many IRR?s as there sign changes.? Only one rate is economically significant in


determining whether the investment is profitable.?????????????????????????????????????? ??????????????????????? D1)Considerations of


uncertainties are: ??????????????????????????????????????????????? ·


50% probability of


Standard Price oil ·


40% probability of


Higher Price oil ·


10% probability of


Lower Price oil And??????????????????????????????????????? ·??? 80%


probability of Standard Reclamation cost?????????????????????????????????????? ·?? 20%


probability of high Reclamation cost ??????????????????????????????????????????????? ·?? 0%


probability of low Reclamation costs ???????????????????????????????????????????????????? Using the above scenarios


the probability of:·


Standard Price /


Standard Reclamation costs = 40% NPV = £5607 ·


Standard Price /


High Reclamation costs = 10% NPV = -£50841 ·


Low Price / Standard


Reclamation costs = 8% NPV = -£210541 ·


Low Price / High


Reclamation costs = 2% NPV = -£266988 ·


High Price /


Standard Reclamation costs = 32% NPV = £113680 ·


High Price / High


Reclamation costs = 8% NPV = £57233It can be noted that the


most likely outcome will be standard price oil / standard reclamation costs


which has a 40% chance.However further calculations


need to be done to make a more informed decision. The calculations of which are


done in excel and are referenced in the appendices.The ENPV = £15930 The Standard deviation =


£96880 The Variance = 9368.58 The Expected Return =


2.343% ?D2)? Using the information, most


likely outcome will be: standard price oil / standard reclamation

costs


which has a 40% chance.The ENPV of £15 930 is the


outcome expected if a project similar to this is undertaken again.? But risk needs to be accounted for, which is


both positive and negative from the mean (£15 930).? The standard deviation of £96 880, is very high which


reflects a large dispersion around the ENPV of £15930, hence greater risk.? Therefore there is a possibility that the final


result being under £15 930.? It could be


£10 930, £5 930 or -£4 030.? On the


other hand there are similar chances of obtaining £30 930, £35 930 or even


higher.As this is a large project,


there is a chance that the firm will incur an economic loss.? Therefore we have a 43.62% probability of


the NPV for the project will be negative.?


That is a 1 in 2 chance of losing money!D3) ???????????????????????????????????????????????????????????????????????????????????????? Probability analysis however


involves juggling with a lot of numbers; therefore decision makers could find


it hard to interpret them.The ENPV gives incomplete


information about project risk by itself because it measures central tendency,


whereas the management maybe concerned with the dispersion of possible outcomes


around the mean.Degree of uncertainty to the


various alternative is viewed in isolation, whereas it is important to take


into account the amount of risk, that each alternative will contribute to the


overall risk of the firm; such portfolio analysis.E)The WACC is useful for


investment appraisal as it used in capital budgeting decisions as a percentage


discount rate, which incorporates the effect of tax shields, to find the NPV of


projects that would not change the risk of the firm, by acting as a handle rate


for capital investments, which give the minimum required return on an


investment, on its discount cashflow calculations.? If the risk is not similar, a firm that invests in projects like


the one being considered is found and the equity cost of capital of that firm


is compared to ours.? The difference


being the firm?s beta compared to ours.?


To be able to use the firms WACC to discount the project, we assume that


the company will continue to home the same capital structure, which can be


classified into two types: (i) all equity and (ii) mixed with where debt and


equity are held in varying proportions.The traditional WACC can be


calculated by:Kd???? D???? +?? Ke???


E ?????? D+E???????? ???? D+EWhere Kd?????? = ???????? cost


of debt Ke


????? = ???????? cost


of equity D


??????? = ???????? proportion


of debt E


??????? = ???????? proportion


of equitySource : J Wyld WACC is calculated using


actual balance sheet data of companies and industries and all the variables in


the formula refers to the whole firm, therefore, when considering investment


appraisal using WACC, the company must be aware that industry costs might be


better than individual firms cost when used for investment appraisal.? Therefore the WACC can be adjusted for


changes in debt ratios according to WACC, debt is constantly rebalanced or


business risk by applying changes to the equation, which can also be used for


beta.Different investments have


different levels of risk, therefore the higher the risk the higher the rate of


return and vice versa.? Therefore the


WACC of 10% to be appropriate for any investment appraisal depends if the project


is of similar risk.? If the level of


risk is higher, then a risk premium should be added.? The CAPM approach provides a starting point.? The risk premium depends on the firms risk


level.? The higher the risk, the greater


the required rate of return or equity.?


The risk level of business and the financial coverage will have an


affect on the risk premium. The CAPM model, states that


the risk premium varies in direct proportion to beta which means all


investments slope along the security market line. See graph 3The expected risk on an


investment with a beta of 0.5 is half the expected risk premium on the market.The firms risk using the


CAPM approach is measured by its systematic risk, the beta and not by its


variance alone, therefore the required rate on an investment is given by: ??????????????????????????????????????????????? kei = r + (Exm ?


r) Where ·


r = risk free rate ·


Exm = the expected


return of the market portfolio ·


???= the ith firms systematic


risk ·


kei = the required rate


of return on an investment of the ith firm. TOTAL WORD COUNT = 1646APPENDICESCalculations for Question ANPV = A projects net contribution to wealth ; present value


minus initial investment. YEAR CASH DISC DISC’TED FLOW FACT. CASH (10%) FLOW 0 -680 1.000 -680.000 1 400 0.909 363.636 2 400 0.826 330.579 3 250 0.751 187.829 4 200 0.683 136.603 5 100 0.621 62.092 6 -700 0.564 -395.132 NET PRESENT VALUE 5.607 ?Definitions for Question BInternal rate of return = Discount rate at which investment


has zero NPV.Calculations for Question DProbability;? Standard Price Oil / Standard Reclamation Costs = (5/10) * (8/10) = 40% Standard Price Oil / High Reclamation Costs = (5/10) * (2/10) = 10% Low Price Oil / Standard Reclamation Costs = (1/10) * (8/10) = 8% Low Price Oil / High Reclamation Costs = (1/10) * (2/10) = 2% High Price Oil / Standard Reclamation Costs = (4/10) * (8/10) = 32% High Price Oil / High Reclamation Costs = (4/10) * (2/10) = 8%The Expected Return = 15933 / 680000 =


2.343%Calculation for D2A negative NPV means a value


less than zero hence we can say that the probability that an NPV will be


negative is given by the formula;z = (0 ? ENPV) / sd = sd


unitsThe equation is measuring


how far from the expected mean value an NPV might be in the left hand direction


of the normal curve.The ENPV = £15930 and the


standard deviation associated with this = £96880. By using the above equation


we can find the number of standard deviation units by which this varies from


the mean relative to zero.? This gives:z = ( 0 ? 15930 ) / 96880 =


-0.16 standard deviation (sd) units.? We


need to know now the probability associated with this number of sd units from


the normal distribution function.? Using


the normal distribution table read down to 0.1 then across to 0.06 to give us


0.16.? The value in the table is


0.0638.? This is not the probability of


a negative NPV, because we are interested in the left hand side of the normal


curve.? To do this we need to subtract


our table value from 0.5 (ie we are only concerned with the left hand tail of


the distribution) so that the probability the NPV will be negative is given in


the table as:(0.5 ? table z) = (0.5 ?


0.0638) = 0.4362 which is 43.6%.100 / 43.6 = 2.2.

Сохранить в соц. сетях:
Обсуждение:
comments powered by Disqus

Название реферата: Business NPV Essay Research Paper The NPV

Слов:2227
Символов:15815
Размер:30.89 Кб.